News Flash

Community News

Posted on: July 22, 2021

Reinhardt Drive Street Reconstruction Project

Reinhardt street reconstruction July 2021

Reinhardt Drive Street Reconstruction Project  

UPDATE 7/29/2021:  If you live on Reinhardt Drive, driveways have been ramped and residents can start parking in their drives immediately. Thank you for your patience during the driveway restriction period. Next up, KHC will remove the remaining asphalt between 50th St. & 48th St. and will be bringing in the rock base. Base asphalt will be placed the first week of August and sidewalk installation will also start in August. 

UPDATE 7/22/2021: Street reconstruction project from Reinhardt Dr. from Pawnee Dr. to W. 48th Street.
If you live on Reinhardt Drive, the driveway restriction period has begun. KHC's plan is to have all curb and driveways poured by Friday, July 23. The cure time over the weekend should allow for driveway access by mid-week of the following week (week of July 26th). KHC will let neighbors know when driveway access will be available again.
We will keep the community informed if these dates shift or change. If you have questions or need to schedule special accommodations please contact Donnie Scharff: dscharff@roelandpark.org.


A street reconstruction project has started on Reinhardt Dr. from Pawnee Dr. to W. 48th Street. The city's contractor (Kansas Heavy Construction) has set up traffic control devices and detour routes.  

 If you live on Reinhardt Drive, the driveway restriction period has begun. KHC's plan is to have all curb and driveways poured by Friday, July 23. The cure time over the weekend should allow for driveway access by mid-week of the following week (week of July 26th). KHC will let neighbors know when driveway access will be available again. 

 We will keep the community informed if these dates shift or change. If you have questions or need to schedule special accommodations please contact Donnie Scharff: dscharff@roelandpark.org.

 This project will entail removal and replacement of sidewalks, curb & gutter, street base and surface as well as minor storm sewer work. Full reconstruction of the street will take place between Pawnee Dr and 50th St. Partial reconstruction will take place on Reinhardt between 50th St & 48th St. Access will be available to residents that live on Reinhardt during the construction. Temporary aggregate will be put in place following the removal of the street. Minor delays can be expected. 

 The completion date for all work is November 2021, weather permitting.

Facebook Twitter Email