Roe Blvd Mid-September Update

Roe Blvd Construction 9.16.2020

There are a some updates to the Roe Boulevard project as of September 16, 2020. 

  • Contractor is working at the intersection of 55th St putting in bases for the new traffic signal controllers;
  • Curbs are being poured between 51st & 48th St this we...
Read on...

Roe 2020
Posted on: September 8, 2020

Roe 2020 Update - September 8, 2020

Roe image 2020

▶️ Westside drives/curbs south of 51st St. are complete and open to residents.

▶️ Eastside drives/curbs from Johnson Dr to 56th St. are complete and back open to residents.

▶️ The team will start the westside sidewalk install south of 51st St.

▶️ Traffic pat...

Read on...

Roe 2020
Posted on: August 13, 2020

Roe 2020 Project Update - Driveways & Curbs

Driveway Replacement 5

Next week the crew will start excavation work on the east side of Roe Blvd., beginning at Johnson Drive and working north. They will do all curb and driveway removals, after removals are complete residents will have a temporary rock access to their drivew...

Read on...